Location Kerrville, TX
CEC served as the civil engineer for the design of the new roadway and drainage facilities. The project included the evaluation of four different alternative alignments for the new taxiway to allow the construction of a CAT I Instrument Landing System (ILS) as part of a separate contract. TxDOT Aviation and the City of Kerrville decided to reconstruct the taxiway at 400’ from the centerline of Runway 12/30 with the future reconstruction of a portion of the taxiway at a greater separation when the runway is lengthened and the Glide Slope Critical Area can be re-graded. A new entrance road was constructed as part of the project due to the reconstruction of the taxiway.